The first FLNGV will have a capacity of up to 2 million tonnes per annum and will utilize the existing 125,000 cubic meters of LNG storage on board the carrier. Keppel will start the FEED study in November and detailed design and engineering is expected to be concluded around mid-2013 when vessel conversion is expected to start. The first unit will be developed through several construction stages in order to accommodate customer requirements and is expected to be ready for production by Q1 2015. Golar retains the option to convert two additional vessels with Keppel under the same agreement. The Company sees its partnership with an experienced shipyard and a production plant provider with significant LNG experience as valuable for minimizing technical risk in the project. This project represents the next phase in Golar's strategy of expanding its presence within the LNG industry. The Company aims to offer its customers unique, flexible and highly economical solutions, thereby capturing a substantially greater share of the overall LNG commodity trade value. The Board anticipates that the first unit can be financed through a combination of existing cash, future cash flow, further drop downs and new debt facilities and presently do not envisage any need for additional equity. Golar's Chairman John Fredriksen said, "Golar helped to open up the LNG market through the introduction of floating receiving terminals which have opened a lot of new markets for LNG. Our FLNGV's will be able to provide a fast-track, cost effective solution for developing new LNG production capacity. We believe this technology will be extremely attractive to companies looking to develop their natural gas assets and we are actively pursuing multiple opportunities. It is Golar's intention to market the solution for field developments as well as for direct production from existing pipeline infrastructure. The Board sees particular opportunities in the African region, where gas prices remain low. Significantly, large quantities of gas are currently being flared and the infrastructure doesn't naturally support large land based LNG investments. The Board is excited about the new business line and sees massive opportunities for growth in the next five to ten years". Golar LNG Limited press release |